A alone can do a work in 20days. B is 25% more efficient than A. A and B started working and worked for 4days. If C alone completed the remaining job in 22days. How many days C alone takes to complete the entire job?
Answers
Answered by
1
Answer:
40 days
Step-by-step explanation:
A alone can do work in 20 days.
B is 25% more efficient than A.
⇒ B can do a work in 16 days.
Let the total unit of work ( LCM of 20 and 16) = 80 units
⇒ A’s one day work = 4
⇒ B’s one day work = 5
As A and B left after working for 4 days.
⇒ Work done by A and B in 4 days = 36 work
⇒ Work left = 44 units is done by C in 22 days.
⇒ C’s one day work = 2 units
∴ 80 units of work can be completed by C alone in 80/2 = 40 days.
Also, if you could please mark this "brainliest" (the crown) it would help a lot! Happy Thanksgiving!!
Similar questions
Biology,
2 months ago
Environmental Sciences,
2 months ago
Math,
5 months ago
Accountancy,
5 months ago
Economy,
10 months ago
Economy,
10 months ago