A alone can do a work in 40 days and ratio of efficiency of B to that of A is 5:4. If A started and worked for 15 days and left then then in how many days will B do the remaining work?
Answers
Answer:
Step-by-step explanation:
A completes in 40 days.
So in 1 day A completes 1/40 th part.
Given the ratio of time taken by A & B for completion of the work is 5:3.
So B will take 40×3/5=24 days to complete the work.
In 1 day B will complete 1/24 th part .
In 1 day both A & B together will complete 1/40+1/24=(24+40)/960=64/960=1/15 th part. So both A & B together will take 1÷1/15=15 days to complete the entire work.
Ans: 15 days.
Answer: 20 Days
Step-by-step explanation:
Given,
- A alone can complete a piece of work in 40 days.
- Ratio of efficiency of work of B to that of A is 5:4.
- A started to work on a piece and left after 15 days.
To Find: The number of days in which B will complete the remaining part of the work that A left after working for 15 days.
Explanation:
- First, we will calculate the number of days in which B alone can complete the same piece of work that A can complete in 40 days by using the efficiency ratio mentioned in the question-statement.
Since Ratio of efficiency of work of B to that of A is 5:4, it means that [5:4::40:x], assuming B complete a piece of work in "x" days.
[Note: Higher effeciency of work means less time to finish a piece of work]
- Therefore, B can finish the same piece of work that A can complete in 40 days in 32 Days.
- Then using the Unitary Method, we will calculate the piece of work A and B can individually complete in one day.
If A can finish in 40 days, 1 whole work,
Then, A can finish in 1 day, (1/40) part of the work.
Similarly, If B can finish in 32 days, 1 whole work,
Then, B can finish in 1 day, (1/32) part of the work.
- Now, as per the question-mentioned condition, A left after working at his own rate for 15 days, i.e.,
A finished part of the work and left.
- B finished the remaining part of the work, working at his own rate.
- Remaining part of the work = part.
- Since, B can finish 1 whole work in 32 days,
Then, B can finish (5/8) part of the work in days.
A can do a work in 15 days and B in 20 days. If they work together on it for 4 days, what fraction of work will be left?
https://brainly.in/question/6500281
A can do a work in 24 days A and B together can finish the work in 6 days then B alone can finish the work in ____ days ?
https://brainly.in/question/15162587
#SPJ2