A alone can do a work in 6 days and B can do the same work in 8 days and with the help of C they finished the same work in 3 days . How they can divide and Rs.3200 and how much C will get
Answers
Answered by
0
Answer:
Hope it is helpful
Step-by-step explanation:
A can do the work in 6 days
B can do the work in 8 days
wit the help of c they completed within 3 days
total amount to be paid = RS.32,000
so,1/x we can use
ATP (According To Problem)
Let, the total work done be 24x
part of work done by A in a day = 24x/6=4x
part of work done by B in a day = 24x/8=3x
part of work done by A,B and C in a day= 24x/3=8x
Work done by C in a day = 8x-4x-3x= x
work done by C in 3 days = 3x
for 24x work amount paid = RS. 32,000
Amount to be paid to C =(32000/24x)3x
= 400/-
~Amount To Be Paid To C is RS. 400/-