Math, asked by ravi1954p, 6 hours ago

A alone can do a work in 6 days and B can do the same work in 8 days and with the help of C they finished the same work in 3 days . How they can divide and Rs.3200 and how much C will get

Answers

Answered by pavulurilr
0

Answer:

Hope it is helpful

Step-by-step explanation:

A can do the work in 6 days

B can do the work in 8 days

wit the help of c they completed within 3 days

total amount to be paid = RS.32,000

so,1/x we can use

ATP (According To Problem)

Let, the total work done be 24x

part of work done by A in a day = 24x/6=4x

part of work done by B in a day = 24x/8=3x

part of work done by A,B and C in a day= 24x/3=8x

Work done by C in a day = 8x-4x-3x= x

work done by C in 3 days = 3x

for 24x work amount paid = RS. 32,000

Amount to be paid to C =(32000/24x)3x

                                        = 400/-

~Amount To Be Paid To C is RS. 400/-