Math, asked by ushananthini, 9 months ago

A alone can do piece ofworkin 35 days .if B is 40% more efficient than A then B will finish work in ------ days​

Answers

Answered by shahidshaikh77388
2

Answer:

14 is the correct answers

Answered by jitendra420156
7

Therefore in 25 days B will finish the work .

Step-by-step explanation:

Given that A alone can do a piece of work in 35 days.

Let total work = 100 units.

B is 40% more efficient than A.

It means B can do 140 units in 35 days.

B can do 1 unit in \frac{35}{140} days

B can do 100 unit in \frac{35\times 100}{140} days

                               = 25 days

Therefore B will finish the work in 25 days.