A alone can finish the work in 10 hours, B alone can finish the work in 12 hours and C alone can finish the work in 15 hours. A, B and C together started working at 11’o clock. After 2 hours A leaves. When will B & C will together will finish the work?
Answers
Answered by
4
they can do the work in 30divided by 9 days
Answered by
0
Answer:
4:20pm
Step-by-step explanation:
A can do the work in 10 hours
⇒A's 1 hour =
B can do the work in 12 hours
⇒B's 1 hour =
C can do the work in 15 hours
⇒C's 1 hour =
Work done by A ,B and C together in 1 hour =
Work done by A ,B and C together in 2 hour =
Amount of work left to do after 2 hours :
Amount of work B and C can do in an hour:
Amount of work done by Band C in one hour =
Find the number of hours B and C need to complete the work:
Number of hours needed = 1/2 ÷ 3/20 = 1/2 x 20/3 = 10/3 hours = 3h 20 mins
A, B and C worked for 2 hours
B and C worked for 3 hours 20 mins
Total duration = 2 hours + 3 hours 20 mins = 5 hours 20 mins
Start time = 11 am
Duration = 5 hours 20 mins
So,End time = 4:20 pm
Thus B and C will finish the work at 4:20pm