A alone completes a piece of work in 4 days and B alone completes it in 6 days.
If A and B work on alternate days and B starts on first day, how many days are
required to complete the work
Answers
Answered by
0
Answer:
12 days are required to complete the work
Step-by-step explanation:
12 days