A&B can do piece of work in 18 days, B&C in 24 days and A&C in 36 days. In how many days, will all of them together complete the work?
Answers
Answered by
0
Answer:
16 days
Step-by-step explanation:
Answered by
0
Answer:
16 days
Step-by-step explanation:
2*8 16 days works required to comolete