Math, asked by srigeedhu1825, 1 year ago

A an do work in 20 days b in 12 days b worked at it for 9 days s can finish the remaining work in

Answers

Answered by shivamchaudhary72
0
both will complete rhe same work in five days
Attachments:
Answered by TheLostMonk
0
A's 1 day's work = 1/ 20


b's 1 day's work = 1/ 12


B's 9 days' work = 9 × 1/ 12


= 9 / 12 = 3/ 4


remaining work = 1 - (3/4) = 1/ 4


A can finish the remaining work in


= (1/ 4) ÷ (1/ 20) = 20 ÷ 4 = 5days


Answer:
--------------

A can finish the remaining work in 5 days.