Math, asked by singhawani18, 9 months ago

A and B ca do a piece of work in 72 days. B and C ca do the same piece of work in 56 days. If A, B , and C work on it for 38 days, 45 days, 42 days respectively. then find the time taken by A alone to do the work​

Answers

Answered by devimanji8685
0

Answer:

a will take 53 days to complete the work

Answered by manojsinghthakur3969
1

Answer:

53 is your answer

Step-by-step explanation:

it takes 53day to complete the work