A and B can can do a piece of work in 40 days Band C in 30 days and c and A in 24 days how long Will it take them to do the work together

Answers

Answered by ShuchiRecites
13
Hello Mate!

A and B do part of work in a day = 1/40

B and C do part of work in a day = 1/30

A and C do part of work in a day = 1/24

( A and B ) + ( B and C ) + ( C and A ) = ( 1/40 + 1/30 + 1/24 )

2A + 2B + 2C = ( 3 + 4 + 5 )/120

2( A and B and C ) = 12/120

A and B and C = 12/120 × 1/2
= 1/20 = 20 days

Hope you got it!☺