A and B can complete a piece of task together in 12 days while A alone can do it in 15
days. They start working together but A leaves 10 days before the completion of the task.
For how many days did A and B work together?​

Answers

Answered by jashirajasmin
2

Answer:

For 2 days they worked together

Answered by sinharita1503
1

Answer:

2

Step-by-step explanation:

only two days they work together