A and B can complete a piece of work in 12 days and 18 days respectively . A begins to do the work and they work alternately one at a time for one day each .The whole work will be completed in. explain and answer
Answers
Answered by
5
[tex]\huge \pink{ \mid{ \underline{ \overline{ \tt Answer :- }} \mid}}[/tex]
Step-by-step explanation:
A and B can complete a piece of work in 12 days and 18 days respectively. Then,
Part of work per day by A and B is 1/12 and 1/18 respectively.
Let n days be required to complete the work. (1 unit)
They alternate on it at a time for one day each. i.e. A and B each work for n/2 days.
Their total work = (n /2) [(1/12)+(1/18)], which is 1.
(n /2) [(1/12)+(1/18)] = 1
(n/24)+ (n/36) =1
n= 72/5
Each of them worked for 72/10 days.
Ans: Whole work will be completed in 14.4 days, which means 14 days and 8 hours.
[tex]\huge \green{ \mid{ \underline{ \overline{ \tt Brainliest :- }} \mid}}[/tex]
Similar questions
Science,
2 months ago
Math,
5 months ago
Math,
11 months ago
World Languages,
11 months ago
Business Studies,
11 months ago