A and B can complete a piece of
work in 12 days and 18 days
respectively. A begins to do the
work and they work alternately one
at a time for one day each. The
whole work will be completed in:
(SSC, 2007)
Answers
Answered by
0
Answer:
30 days
Step-by-step explanation:
please mark me as brainlist
Answered by
1
Answer:
Let the work be 36 units
Per day work be done by A = 36/12=3 units of work per day
Per day work be done by B = 36/18=2 units of work per day
therefore in two days (2+3) = 5 units of work will be done .
therefore nearest units of work done by them in 7 cycles of 2 day each=(5*7)= 35 units in 14 days(7×2)
left 1 unit of work will be done by A in 12/36 =1/3 of day
= Total time for work will be 14 and 1/3 Days
Hence total time taken will be days
HOPE IT HELPS YOU