A and B can complete a task in 12 days. However. A had to leave a few days before thetask was completed and hence it took 16 days in all to complete the task. If A alone couldcomplete the work in 21 days, how many days before the work getting over did
A leave
Answers
Answered by
1
Answer:As B leaves 5 days before work, that means for remaining 5 days , A work alone and complete the work.
Step-by-step explanation:
Saddam255:
explain this solution
Answered by
16
B can alone do the work =
1/ (1/12 -1/21)
1/B .......= 7-4/84=3/84 = 1/28
B......28 DAYS
Let A worked X days
So
Work done by A + Work done by B =1
X/21 +16/28 =1
X/21 = 12/28
X=9
A worked for 9 days means A left work before ( 16-9=) 7 days of completion.