Math, asked by sonighutam1234, 5 months ago

A and B can complete a task together in 35 days. If A completes 5/7 of the task and then leaves the rest for B, it will take a total of 90 days to complete the task. How many days would it take A to complete the entire work by herself?​

Answers

Answered by vivekbt42kvboy
2

Step-by-step explanation:

A and B can complete a task together in 35 days. If A completes 5/7 of the task and then leaves the rest for B, it will take a total of 90 days to complete the task. How many days would it take A to complete the entire work by herself?

Kickstart your career with Manipal's UGC-recognised online BCA!

Let us assume that A completes the work alone in X number of days.

Work done by A and B in 1 day = 1/35 (given)

Work done by A alone in 1 day = 1/X

Work done by B alone in 1 day = (1/35) - (1/X) = (X - 35) / 35X

No. Of days taken by A for doing 5/7 of work = (5/7) / (1/X) = 5X/7 days.

No. Of days taken by B for doing remaining 2/7 of work = (2/7) / {(X - 35) / 35X}

= 70X / 7(X - 35) = 10X / (X - 35) days

Therefore,

(5X/7) + {10X / (X - 35)} = 90 days (given)

Rearranging the equation we get,

5X(X-35) + 70X = 630 (X - 35)

Or 5 X^2 - 175X + 70X = 630X + 22050

Or X^2 - 147X + 4410 = 0

Solving for X,

(X - 105) (X - 42) = 0

It can be seen that X can not be 42.

So X must be 105 days.

Ans. A alone can finish the work in 105 days.

It can be shown that B alone can do the work in 52.5 days.

Verification:

A does 5/7 of work in (105*5/7) = 75 days.

B does the remaining work of 2/7 in (52.5*2/7) = 15 days.

So total number of days = 90

Similar questions