A and B can complete a work in 15 days and 10 days respectively they started doing the work together but after 2 days we had to leave and a alone completed the remaining work then the whole work was completed in
Answers
Answered by
3
Answer:
12 days
Step-by-step explanation:
A,
in 15 days do a work
therefore in 1 day he does=1/15
B,
in 10 days do a work
therefore in 1 day he does=1/10
(A+B),
in 1 day do (1/15+1/10)=2+3/30=5/30=1/6
in 2 days do=2×1/6=1/3
rest work,
1-1/3=2/3
A,
1/15 does in 1 day
therefore 2/3 does=15×2/3=10days
whole work=10+2=12days