Math, asked by anshu1122a, 1 year ago

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in:

8 days
10 days
12 days
15 days

Answers

Answered by Anonymous
7

Answer:

♠ The correct option is C.

Step-by-step explanation:

♦ Let total work be 30 units (LCM of 10 and 15).

In one day, A can do 2 units of work and B can do 3 units of work.

In one day, both A and B can do 5 units of work.

In two days, A and B will complete 10 units of work. Remaining 20 units can be completed by A in 10 days (at rate of 2 units per day).

Hence, whole work will be completed in 12 days.

Answered by Anonymous
13

Answer:

12 days

Step-by-step explanation:

A and B can complete a work in 15 days and 10 days respectively.

Their 1 day work = (1/15 + 1/10) = 1/6

After 2 days B had to leave.

Work done in that 2 days = 1/6 * 2 = 1/3.

Remaining work = 1 - 1/3 = 2/3

A alone completed the remaining work.

=> 15 * 2/3

=> 10 days

Hence, total time taken = 12 days.

#Hope my answer helped you!