A and B can complete a work in 6 days.A can alone do it in 10 days. Then B can alone do the
work in how many days?
16 days
14 days
15 days
Answers
Answered by
8
GIVEN :-
- A and B can complete work in 6 days
- Work done by A alone is 10days
TO FIND :-
- Work done by B alone
SOLUTION:-
Let ,
Work done by B alone be x
So,
- One day work of A&B is
- One day work of A is
- One day work of B is
One day work done by A&B together = one day work of A + one day work of B
LCM OF 6, 10 is 30
One day work of b is 1/15
Total work done by b is 15
option (c)