A and B can complete a work in 6 days. B and C can complete the same work in 8 days. C and A can complete in 12 days. How many days will take for A, B and C combined together to complete the same amount of work ?
Answers
Answer:
73.6 days
Step-by-step explanation:
Let A can complete whole work in x days
Let B can complete the same work in y days
Let c can complete the whole work in z days
=In x days A can complete the whole work (1)
x days =1 part
1 days = 1/x part
In 6 days = 6/x part
In y days B can complete the whole work
y days = 1 part
1 days = 1/y part
6 days = 6/y part
According to the question A and B can complete the whole work in 6 days
= 1/x + 1/y= 6
6/x + 6/y= 1
According to the question B and C can complete the whole work in 8 days
8/y+ 8/z=1
According to the question A and C can complete the whole work in 12 days
12/x+12/z= 1
Let 1/x = p ,1/y= q and 1/z = r
6p+ 6q = 1
8q+8r=1
12p+12r= 1
:p=1-6q/6
:r=1-8q/8
putting tese values in eq....3
12-72q/6+12-96q/8=1
q=5/48
similarly,r= 1/48 and p= 1/16
1/x=1/16
and x = 16, 1/y = 5/48 and y = 9.6
1/48= 1/z, and z = 48
Hence ABC, together can complete the same work= sum of x,y and z= 48+16+9.6=73.6 days ✓ Ans