Math, asked by dineshsekar1403, 5 months ago

A and B can complete the work in 25 days and 20 days respectively. A alone started working but after 10 days B joined. total works will be completed in how many days ?​

Answers

Answered by ratnagupta79
0

Answer:

Your answer is 20/3days

HOPE IT HELPS YOU