A and B can complete the work individually in 12 days and 18 days. they started doing the work together but after 4 days A had to leave and B alone completed the remaining work.the whole work was completed in
Answers
Answered by
7
Answer:
12
Step-by-step explanation:
4/12 +x/18 =1
after lcm
6+x
___ =1
18
6+x=18
x=12
Answered by
0
Answer:
Step-by-step explanation:
It is given that A can complete the work individually in days
B can complete the work individually in days
Units of work is calculated by finding the LCM
LCM of is
There are units of work.
Efficiency of A units
Efficiency of B units
Both can complete units is a day when work together.
They work together for days units
Remaining units
It is done by B only.
As B's efficiency is , it is done in days.
Work is completed in days.