Math, asked by Garvitbagree29, 8 months ago

A and B can completed a piece of work in 12 days
and 24 days respectively. After A had worked for
6 days, B joined him, and then they completed the
work. How much should A receive as his share from
the total amount of Rs. 180 paid for completing the
work?
(1) Rs. 120
(2) Rs.135
(3) Rs.100
(4) Rs.150​

Answers

Answered by sambhavpowar
2

Answer:

Rs.120

Step-by-step explanation:

Because they will complete it in 9 days and A worked for 6 days first.

Please mark it as brainliest.

Answered by sdrb18907
1

Answer:

120 is the ans

plizz Mark as brainliest

☺️☺️