a and b can do a given piece of work in 8 days b and c can do the same work in 12 days and abc
Answers
Answered by
0
Answer:
ádasdasdasda
Step-by-step explanation:
Answered by
0
Answer: this question is actually incomplete .. the question is 1] A and B can do a given piece of work in 8 days B and C can do the same work in 12 days and a b c complete it in 6 days in how many days can A and C finish it
a+b=1/8;b+c=1/12;a+ b+c=1/6
1/8+1/12=20/96=5/24-1/6
5-4/24=1/24 1/24=24days
So a and c can do the work in 24 days
Step-by-step explanation: