Math, asked by Kushalgubba8089, 1 year ago

A and b can do a job in 20 days and 25 days respectively. They work on alternate days, a beginning the work, in how many days will the work be finished

Answers

Answered by khushbu7863
0

Answer:

9days

Step-by-step explanation:

20/25=4/5 . and 5+4=9