A and B can do a job in 6 days, B and C in 9 days, and A and C in 12 days. How much time
will they take to complete the job if they all work together? How long will each of them take
to do the job?​

Attachments:

Answers

Answered by pastimeplays
18

Answer:

\frac{72}{13} days

Step-by-step explanation:

Let us give the job a value of 1.

A and B require 6 days to finish the job

⇒A and B finish  \frac{1}{6} of the job in 1 day.

A + B = \frac{1}{6}

Similarly we can say that,

B + C =  \frac{1}{9} and

A + C = \frac{1}{12}

Adding all of these,

A + B + B + C + C + A = \frac{1}{6} +  \frac{1}{9} +\frac{1}{12}

2A + 2B + 2C = \frac{6+4+3}{36}

2(A + B + C) = \frac{13}{36}

A + B + C = \frac{13}{72}

Therefore, they can complete the work in \frac{72}{13} days.

Answered by guruprasadjena76
4

Answer:

Is this question from the book "Essential ICSE Mathematics for Class 8"?

Step-by-step explanation:

Bcoz I am also having the same book as I am from Class-8.