Math, asked by vishalagarwal48490, 9 months ago


A and B can do a job together in 25 days. After 15 days of working together, B leaves. If A
completes the remaining part of the job in 20 days, how long would each take to complete
the job, working separately?​

Answers

Answered by NIPUN174
19
Here is the answer mate

See the question says
A and B can do a job together in 25 days. After 15 days B leaves. If A completes the remaining part of the job in 20 days how long would each take to complete the job, working separately?

See if both A and B do work in 25 days so if B leaves then all the work is to be done by A
So it would take A double time to do the work so it should take 50 days to do the work instead of 25 days.

PLZ MARK ME THE BRAINLIEST IF MY ANSWER HELPS.
Answered by rakhipriya
89

Step-by-step explanation:

(A+B)'s one day work = 1/25

amount of work completed in 15 days = 15×1/25

= 3/5

remaining work = 1-3/5 = 2/5

according to the question,

A finish the remaining 2/5 part of the work in 20 days.

therefore, time taken by A to finish the work alone = 20÷2/5 = 50 days

now,

A's one day work + B's one day work = (A+B)'s one day work

1/A + 1/B = 1/25

1/50 + 1/B = 1/25

1/B = 1/25-1/50

1/B = 1/50

therefore, time taken by B to complete the whole work = 50 days

Similar questions