A and B can do a job together in 25 days. After 15 days of working together, B leaves. If A completes the remaining part of the job in 20 days, how long would each take to complete the job, working separately?
Answers
Answer:
- A takes 50 days to complete the work.
- B also takes 50 days to complete the work.
Step-by-step explanation:
Given that:
- A and B can do a job together in 25 days.
- After 15 days of working together, B leaves.
- A completes the remaining part of the job in 20 days.
To Find:
- How long would each take to complete the job working separately?
We know that:
- Total work = 1
- A and B's 25 days work = 1
- A and B's one day work = 1/25
A and B working together for 15 days,
- A and B's 15 days work = 15/25 = 3/5
Remaining work = Total work - work done
- Remaining work = 1 - 3/5
- Remaining work = 5/5 - 3/5
- Remaining work = 2/5
Remaining work completed by A in 20 days,
- A's 20 days work = 2/5
- A's one day work = 2/(5 × 20) = 1/50
- A's 50 days work = 50/50 = 1
So, A can complete a work separately in 50 days.
Let B can complete the work separately in x days.
- B's one day work = 1/x
A's one day work + B's one day work = (A + B)'s one day work
→ 1/50 + 1/x = 1/25
→ 1/x = 1/25 - 1/50
→ 1/x = 2/50 - 1/50
→ 1/x = 1/50
→ x = 50
Therefore,
- B can complete the work separately in 50 days.
Given :- A and B can do a job together in 25 days. After 15 days of working together, B leaves. If A completes the remaining part of the job in 20 days .
To Find :- How long would each take to complete the job, working separately ?
Solution :-
Let's solve this problem in a very simple way.
given that,
→ In 25 days (A + B) completes = 1 work.
so,
→ In 1 day (A + B) completes = (1/25) work .
then,
→ In 15 days they completes = (1/25) * 15 = (3/5) work .
so,
→ Left work to be complete now = 1 - (3/5) = (2/5) work.
given that,
→ Left (2/5) work done by A alone in = 20 days.
then,
→ Total 1 work will done by A alone in = 20 * (5/2) = 50 days (Ans.)
therefore,
→ Total 1 work done by B alone in = (1/25) {A + B / day work} - (1/50){ A alone / day work.} = (1/25) - (1/50) = 50 days. (Ans.)
Hence, Both A and B will take 50 days to completes the Job when working separately .
Learn more :-
Giri does 2/5 piece of work in 10 days. Ankit does 5/9 of the remaining work in 15 days and Gaurav finishes remaining wo...
https://brainly.in/question/21025557
Shivam alone can do a work in 12 days and Maanik alone can do it in, 15 days. Both started the work together and after w...
https://brainly.in/question/14687371