a and b can do a piece of a work in 12 days,b and c in 15 days, b and a in 20 days . how much time will alone take it to finish the work?
Answers
Answered by
2
time taken by a + b to finish the work=12 days
Work done by a+b in 1 day=1/12
Time taken by b+c to to finish the work =15 days
Work done by b+c in 1 day=1/15
Time taken by c+a to finish the work =20 days
Work done by c+a in 1 day=1/20
Time taken by (a+b) (b+c) (c+a) =1/12+1/15+1/20=(5/60+4/60+3/60)=1/5
Time taken by2(a+b+c) in 1 day=1/5
Time taken by (a+b+c) in 1 day=1/5*2=1/10
Time taken by (a+b+c) =1/1/10=10 days
Work done by a+b in 1 day=1/12
Time taken by b+c to to finish the work =15 days
Work done by b+c in 1 day=1/15
Time taken by c+a to finish the work =20 days
Work done by c+a in 1 day=1/20
Time taken by (a+b) (b+c) (c+a) =1/12+1/15+1/20=(5/60+4/60+3/60)=1/5
Time taken by2(a+b+c) in 1 day=1/5
Time taken by (a+b+c) in 1 day=1/5*2=1/10
Time taken by (a+b+c) =1/1/10=10 days
Answered by
3
Given:
A and B can do a piece of work in = 12 days
Work done by A and B in 1 day = 1/12
B and C can do a piece of work in = 15 days
Work done by B and C in 1 day = 1/15
A and C can do a piece of work in = 20 days
Work done by A and C in 1 day = 1/20
Solution:
On adding A, B and C we get,
2(A+B+C)’s one day work
= 1/12 + 1/15 + 1/20
= (5+4+3)/60 (by taking LCM for 12, 15 and 20 which is 60)
= 12/60
= 1/5
A+B+C one day work = 1/(5×2) = 1/10
Knowing that:
Work A can do in 1 day
= (A+B+C)’s 1 day work – (B+C)’s 1 day work
= 1/10 – 1/15
= (3-2)/30 (by taking LCM for 10 and 15 which is 30)
= 1/30
Answer:
∴ A alone can finish the work in = 1/(1/30) = 30day.
Similar questions