A and B can do a piece of eork separately in 8 and 12 hours. If they work alternate hours, A starting, when will the work be finished
Answers
Answered by
2
Answer:
9 and a half hours.
Explanation:
If A takes 8 hours to complete it, they work at a rate of 1/8th of the work per hour. Then, if B takes 12 hours, they take 1/12th of an hour.
Hour 1 (A): 1/8
Hour 2 (B): 1/8 + 1/12= 5/24
Hour 3 (A): 5/24 + 1/8= 8/24
Hour 4 (B): 8/24 + 1/12=10/24
Hour 5 (A): 10/24 + 1/8=13/24
Hour 6 (B): 13/24 + 1/12=15/24
Hour 7 (A): 15/24 + 1/8=18/24
Hour 8 (B): 18/24 + 1/12=20/24
Hour 9 (A): 20/24 + 1/8=23/24
Now, we only need another 1/24th, or half of 1/12th. Therefore, you have the full 9 hours and a half.
Good luck, message me if you want more deets or a maths tutor on Discord (Steven Universe Naomi#6511) :D