A and B can do a piece of work in 10 days and 15 days respectivily. They work togather for 3 days and then B leaves. Then how many days
take to finish the remainig work by A ?
Answers
Answered by
0
Answer:
Step-by-step explanation:
A&B together can do the work in = 1/10 + 1/15 = 3 + 2 / 30 = 5/30 = 1/6.
A& B together can do the work in 6 days.
Given, A & B worked together for 3 days, before B leaves.
So amount of work completed in 3 days = 3 * 1/6 = 1/2 part of work.
Amount of work left over = 1 -1/2 = 1/2 part of work.
The time taken by A to complete remaining work = 1/2 * 10 = 5 days.