A and B can do a piece of work in 10 days. B and C can do it in 12 days. A and C can do it in 15 days. How long will A take to do it alone?
A. 20 days
B. 24 days
C. 30 days
D. 40 days
Answers
Answered by
3
Answer:
one day work of A and B=1/10 _______1
one day work of B and C=1/12 _______2
one day work of C and A=1/15 _______3
on adding eq 1 and 3
one day work of (A+B+C+A)=1/10+1/15
" " " " (2A+B+C) =3+2/30
" " " " " =5/30=1/6
put the value of eq 2 i.e one day work of B and C
one day work of 2A+1/12=1/6
" " " " 2A=1/6-1/12
" " " " 2A=2-1/12=1/12
one day work of A=1/(12×2)=1/24
work done by A=1÷1/24=24 days