.A and B can do a piece of work in 10 days, B and C can do it in 15 days and A and C together
can do it in 12 days. How long will they take to do it together? How long will B take to do it
alone?
Answers
Answered by
3
Step-by-step explanation:
A + B = 10 , B+C = 12 , A+C = 15
Now finding LCM which we would consider as total work , LCM = 60 = total work
Now , Efficiency of A + B in 1 day = 60/10 so 6.
Similarly , B+C = 5 and A+C = 4.
add all of the efficiency
(A+B) + ( B+C) + ( A+C ) = 5+4+6
2 ( A+ B+ C ) = 15
A+B+C = 15/2 , THIS IS EFFICIENCY
NOW, TIME = TOTAL WORK / EFFICIENCY
TIME = 60* 2 /15 = 8 days.
Answered by
1
A + B + C = 8 Days
B = 24/5 Days