A and b can do a piece of work in 10 days, b and c in 12 days and c and a in 15 days. In how many days will they complete the work if all three of them work together?
sivaprasath:
actually 8
Answers
Answered by
1
24 days
(A + B)’s 1 day’s work
(B + C)’s 1 day’s work
(C + A)’s 1 day’s work
On adding,
2(A + B + C)’s 1 day’s work
∴ (A + B + C)’s 1 day’s work
∴ A’s 1 day’s work
∴ A alone will complete the work in 24 days.
Answered by
0
hence 8days complete 3 of them
Attachments: