Math, asked by shiv5017, 1 year ago

A and b can do a piece of work in 10 days with a alone doing it in 15 days alternative

Answers

Answered by SamriddhaChandra
2
we have,
1 day work done by a = 1/15
also,
1 day work done by (a + b) = 1/10

clearly,
1 day work of B = 1 day work done by (a + b) - 1 day work done by a
= 1/10 - 1/15
= 1 / 30

hence, B takes 30 days to complete the work.

Although, you didn't ask the question completely, I still tried to guess what you question my be.

IF THERE IS ANY MISTAKE THEN SORRY