A and B can do a piece of work in 12 day B and C in 15 days and C and A in 20 days.How much time will A take alone to finish the job
Answers
Answered by
1
this is your solution okkkkkkkkk
Attachments:
Answered by
6
Answer:
Step-by-step explanation:
(A + B)’s 1 day’s work = 1/12
(B + C)’s 1 day’s work = 1/15
(C + A)’s 1 day’s work = In 1/20
On adding,
2(A + B + C)’s 1 day’s work =1/12+1/15+1/20=5+4+3/60=12/60
=1/5
∴ (A + B + C)’s 1 day’s work = 1/10
∴ A’s 1 day’s work = 1/10-1/15=3-2/30
=1/30
∴ A alone will complete the work in 30 days