Math, asked by CharanMultani6475, 1 year ago

A and b can do a piece of work in 12 days and 16 days respectively. both work for 3 days and then a goes away. find how long will b take to complete the remaining work

Answers

Answered by Anonymous
3
please mark it as a brainliest answer