A and B can do a piece of work
in 12 days and 16 days
respectively. Both work for 3 days
and then A goes away. Find how
long will B take to complete the
remaining work?
Answers
Answered by
1
Answer:
9 days B Take to do reaming work
Answered by
0
Answer:
9 days
Step-by-step explanation:
A--------12 days-------------4---------LCM of 12 and 16 = 48
B---------16 days-------------3---------LCM of 12 and 16 = 48
3 day work of A + B = 21 ---------( 7 × 3 )
Remaining Work = 48 - 21 = 27
let B work for x days to complete the remaining work.
1 day work of B is 3 .
3 × X = 27
X = 9 days