Math, asked by HemanthKapa, 10 months ago

A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. How long will

each take separately to do the same work?​

Answers

Answered by Anonymous
68

Answer :-

A takes 30 days, B takes 20 days and C takes 60 days if each works separately.

Solution :-

Let the A's one day work be 1/A

Let the B's one day work be 1/B

Let the C's one day work be 1/C

Number of days A and B needed to finish the work = 12

A and B one day work = 1/12

⇒ 1/A + 1/B = 1/12 ----(1)

Number of days B and C needed to finish the work = 15

B and C one day work = 1/15

⇒ 1/B + 1/C = 1/15 ---(2)

Number of days C and A needed to finish the work = 20

C and A one day work = 1/20

⇒ 1/C + 1/A = 1/20 ---(3)

Adding (1), (2) and (3)

⇒ 1/A + 1/B + 1/B + 1/C + 1/C + 1/A = 1/12 + 1/15 + 1/20

⇒ 2/A + 2/B + 2/C = (5 + 4 + 3)/60

⇒ 2(1/A + 1/B + 1/C) = 12/60

⇒ 1/A + 1/B + 1/C = 12/(60 * 2)

⇒ 1/A + 1/B + 1/C = 1/(5 * 2)

⇒ 1/A + 1/B + 1/C = 1/10 --(4)

i) 1/C = 1/10 - (1/A + 1/B)

[From (4)]

⇒ 1/C = 1/10 - 1/12

Since 1/A + 1/B = 1/12

⇒ 1/C = (6 - 5)/60

⇒ 1/C = 1/60

⇒ C = 60

ii) 1/B = 1/10 - (1/C + 1/A)

[From (4)]

⇒ 1/B = 1/10 - 1/20

Since 1/C + 1/A = 1/20

⇒ 1/B = (2 - 1)/20

⇒ 1/B = 1/20

⇒ B = 20

iii) 1/A = 1/10 - (1/B + 1/C)

[From (4)]

⇒ 1/A = 1/10 - 1/15

Since 1/B + 1/C = 1/15

⇒ 1/A = (3 - 2)/30

⇒ 1/A = 1/30

⇒ A = 30

Therefore A takes 30 days, B takes 20 days and C takes 60 days if each works separately.

Answered by Anonymous
96

A and B together do a work in 12 days.

Work done by A and B in one day = \dfrac{1}{12} days

B and C together do a work in 15 days.

Work done by B and C in one day = \dfrac{1}{15} days

C and A together do a work in 20 days.

Work done by C and A in one day = \dfrac{1}{20} days.

We have to find how many days will each take separately to do the same work.

According to question,

Both A and B do a work in 12 days and in one day they do \dfrac{1}{12} of the work.

=> \dfrac{1}{A} + \dfrac{1}{B} = \dfrac{1}{12} _______ (eq 1)

Both B and C do work in 15 days and in one day they d \dfrac{1}{15} of the work.

=> \dfrac{1}{B} + \dfrac{1}{C} = \dfrac{1}{15} _______ (eq 2)

Both C and A do work in 20 days and in one day they d \dfrac{1}{20} of the work.

=> \dfrac{1}{C} + \dfrac{1}{A} = \dfrac{1}{20} _______ (eq 3)

Now,

Add (eq 1), (eq 2) and (eq 3)

=> \frac{1}{A} + \frac{1}{B} + \frac{1}{B} + \frac{1}{C} + \frac{1}{C} + \frac{1}{A} = \frac{1}{12} + \frac{1}{15} + \frac{1}{20}

=> \dfrac{2}{A} + \dfrac{2}{B} + \dfrac{2}{C} = \dfrac{5\:+\:4\:+\:3}{60}

=> 2\bigg(\dfrac{1}{A}  \:  +  \:  \dfrac{1}{B}  \:  +  \:  \dfrac{1}{C}  \bigg) = \dfrac{12}{60}

=> \dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} = \dfrac{1}{5\:\times\:2}

=> \dfrac{1}{A} + \dfrac{1}{B} + \dfrac{1}{C} = \dfrac{1}{10}

A, B and C together do work in 10 days.

Now,

• A and B do work in 12 days.

So, wrok done by C = Work done by all three in one day together - Work done by A and B in one day

=> \dfrac{1}{C} = \dfrac{1}{10} - \dfrac{1}{12}

=> \dfrac{1}{C} = \dfrac{6\:-\:5}{60}

=> \dfrac{1}{C} = \dfrac{1}{60}

C do wrok in 60 days.

• B and C do work in 15 days

So, work done by A = Work done by all three in one day together - Work done by B and C in one day

=> \dfrac{1}{A} = \dfrac{1}{10} - \dfrac{1}{15}

=> \dfrac{1}{C} = \dfrac{3\:-\:2}{30}

=> \dfrac{1}{C} = \dfrac{1}{30}

A do work in 30 days.

• C and A do work in 20 days

So, work done by B = Work done by all three in one day together - Work done by C and A in one day

=> \dfrac{1}{B} = \dfrac{1}{10} - \dfrac{1}{20}

=> \dfrac{1}{B} = \dfrac{2\:-\:1}{20}

=> \dfrac{1}{B} = \dfrac{1}{20}

B do work in 20 days.

Similar questions