A and B can do a piece of work in 12 days, B and C in 15 days, C and A in 20 days. How long will
each take separately to do the same work?
Answers
Answer :-
A takes 30 days, B takes 20 days and C takes 60 days if each works separately.
Solution :-
Let the A's one day work be 1/A
Let the B's one day work be 1/B
Let the C's one day work be 1/C
Number of days A and B needed to finish the work = 12
A and B one day work = 1/12
⇒ 1/A + 1/B = 1/12 ----(1)
Number of days B and C needed to finish the work = 15
B and C one day work = 1/15
⇒ 1/B + 1/C = 1/15 ---(2)
Number of days C and A needed to finish the work = 20
C and A one day work = 1/20
⇒ 1/C + 1/A = 1/20 ---(3)
Adding (1), (2) and (3)
⇒ 1/A + 1/B + 1/B + 1/C + 1/C + 1/A = 1/12 + 1/15 + 1/20
⇒ 2/A + 2/B + 2/C = (5 + 4 + 3)/60
⇒ 2(1/A + 1/B + 1/C) = 12/60
⇒ 1/A + 1/B + 1/C = 12/(60 * 2)
⇒ 1/A + 1/B + 1/C = 1/(5 * 2)
⇒ 1/A + 1/B + 1/C = 1/10 --(4)
i) 1/C = 1/10 - (1/A + 1/B)
[From (4)]
⇒ 1/C = 1/10 - 1/12
Since 1/A + 1/B = 1/12
⇒ 1/C = (6 - 5)/60
⇒ 1/C = 1/60
⇒ C = 60
ii) 1/B = 1/10 - (1/C + 1/A)
[From (4)]
⇒ 1/B = 1/10 - 1/20
Since 1/C + 1/A = 1/20
⇒ 1/B = (2 - 1)/20
⇒ 1/B = 1/20
⇒ B = 20
iii) 1/A = 1/10 - (1/B + 1/C)
[From (4)]
⇒ 1/A = 1/10 - 1/15
Since 1/B + 1/C = 1/15
⇒ 1/A = (3 - 2)/30
⇒ 1/A = 1/30
⇒ A = 30
Therefore A takes 30 days, B takes 20 days and C takes 60 days if each works separately.
A and B together do a work in 12 days.
Work done by A and B in one day = days
B and C together do a work in 15 days.
Work done by B and C in one day = days
C and A together do a work in 20 days.
Work done by C and A in one day = days.
We have to find how many days will each take separately to do the same work.
According to question,
Both A and B do a work in 12 days and in one day they do of the work.
=> + = _______ (eq 1)
Both B and C do work in 15 days and in one day they d of the work.
=> + = _______ (eq 2)
Both C and A do work in 20 days and in one day they d of the work.
=> + = _______ (eq 3)
Now,
Add (eq 1), (eq 2) and (eq 3)
=> + + + + + = + +
=> + + =
=> =
=> + + =
=> + + =
A, B and C together do work in 10 days.
Now,
• A and B do work in 12 days.
So, wrok done by C = Work done by all three in one day together - Work done by A and B in one day
=> = -
=> =
=> =
C do wrok in 60 days.
• B and C do work in 15 days
So, work done by A = Work done by all three in one day together - Work done by B and C in one day
=> = -
=> =
=> =
A do work in 30 days.
• C and A do work in 20 days
So, work done by B = Work done by all three in one day together - Work done by C and A in one day
=> = -
=> =
=> =
B do work in 20 days.