Math, asked by s20776aindraneel0082, 6 hours ago

A and B can do a piece of work in 12 days. B and C in 16 days. After A alone worked on it for 5 days followed by B alone for 7 days, C finished in 13 days. In how many days can each do it separately, if they work alone?​

Answers

Answered by sspersiaa
1

Answer:

A worked for 5 days and

B worked for 7 days

If A and B Work together for 5 days

they would complete 4×5=20 units

remaining work = 48−20

=28 units

Now B has to work for 2 more days and if he does it along

with C for 2 days. Then, both would complete (3×2)=6

units of work.

work left = 28−6=22 units

Now C completes in 13−2=11 days

So, C works2211 = 2 units / day

(efficiency) and B+Cdoes 3 units / day (efficiency)

So B does 1 unit/day

B will complete the whole work in 481= 48 day

Step-by-step explanation:

hope my answer help you

Similar questions