A and B can do a piece of work in 12 days, C and A in 20 days and B and C in 15 days, then in how many days will they finish it working together?
a)20days
b)5days
c)15days
d)10days
Answers
Answered by
0
10 days
Step-by-step explanation:
A and B can do a piece of work in 12 days
It means A and B can do 1/12 of work in one day.
C and A in 20 days
B and C in 15 days
(A+B) + (C+A) + (B+C) = 2 (A+B+C)
If 2 (A+B+C) = 5 days
A + B + C = 5 * 2 = 10 days
(Time is inversely proportional to manpower. so we multiply 2 with 5 days.)