Math, asked by niranjanbaskey1528, 11 months ago

A and B can do a piece of work in 12 days, which B and C can do in 16 days. After A has been working for 5 days and B for 7 days, C finishes it in 13 days. In how many days C alone can finish the work?​

Answers

Answered by palwindersaini961
2

Answer:

Lcm of (12,16) = 48 units <--total work

So A+B = 48/12 = 4 units per day

B+C = 48/16 = 3 units per day

Now,

5A+7B+13C = 48 units

5 (A+B)+2 (B+C)+11C = 48

5 (4)+2 (3)+11C = 48

20+6+11C = 48

11C = 22

C = 2 units

So C does 2 units of work daily

So total time required to complete work alone is 48/2 = 24 days

Step-by-step explanation:

please mark my answer as a brain list and also follow me please like it if it helped you....

Answered by prapti15
0

Step-by-step explanation:

A+B=12days.

(A=5days,B=days)

(A + B) one day work = 100/12 = 8.33% per day

B+C=16days

(B + C) one day work = 100/16 = 6.25% per day.

(A + B)'s 5 days work + (B + C)'s 2 days work + C's 11 days work = 1

therefore.5 days work of B has been included with A and 2 das work of C has been included with B

=(8.33 * 5 )+ (2 *6.25) + C's 11 days work = 100%

=C's 13 days work = 100 - 41.66 - 12.5 = 45.84%

=one day work of C = 45.84/11 = 4.16%

=C can done work = 100/4.16 = 24 days

therefore, C finish it's work in 24 days

Similar questions