A and B can do a piece of work, in 15 days and 20 days respectively.
Find,
(i) The work done by A in 3 days.
(ii) The work left after A has worked for 3 days.
(iii) The number of days that B will take to complete the remaining work.
Answers
Answered by
0
Answer:
1. 1/5 part
2. 4/5 part
3. 16