A and B can do a piece of work in 15 days; B and C can do it in 12 days while C and A can finish it 20 days; in how many days will A,B,C finish it working together?

Answers

Answered by kvnmurty
2
10 days.
A, B , C can complete the work in a, b , c days respectively by working alone.
1/a + 1/b = 1/15      1/b + 1/c = 1/12      1/c + 1/a = 1/20
Add these equations :  2 [ 1/a + 1/b + 1/c ] = 1/15 + 1/12 + 1/20  = 1/5
     1/a + 1/b + 1/c = 1/10
A, B,C can do 1/10 work per day.  so 10 days to complete.
Answered by Neelam27
0
A+B= 15
B+C=12
C+A=20
A+B+C=?
SO,
ans is 5 days.