A and B can do a piece of work in 16 days and A alone can do it in 48 days. How long will it be take to complete the work?
Answers
Answered by
1
Answer:
24 days
Step-by-step explanation:
A+B 's day work =1/16
A's day work =1/48
B 's work =1/16-1/48 =1/24