A and B can do a piece of work in 18 days B and C can do in 24 days and a and c can do in 36 days then what time can they do it all working together
Answers
Answered by
0
Answer is 16 days
I guess
Right answer please leave thanks
Answered by
1
Answer:
(A+B) 's 1days work=1/18..(i)
(B+C)'s 1days work=1/24..(ii)
(A+C)'s 1 days work=1/36..(iii)
Add(i),(ii)&(iii),
2(A+B+C)' s 1days work=
1/18+1/24+1/36= 1/8
(A+B+C) 1days work= 1/8÷2=1/16