. A and B can do a piece of work in 18 days; B and C can do it in 24 days while C and A can
finish it in 36 days. In how many days can A, B, C finish it, if they all work together?
Aand Bando
даа
Answers
Answered by
2
(A+B)'s 1 day work = =1/18
(B+C)'s 1 day work = =1/24
(C+A)'s 1 day work = =1/36
2 (A+B+C)'s 1 day's work = 1/8
Therefore, (A+B+C)'s 1 day's work = 1/16
Hence time taken by them to do this work together = 16 days