Math, asked by pratimanasabe, 4 months ago

A and B can do a piece of work in 20 and 16 respectively. if they work on alternate days each starting with A in how many days was the work completed?

Answers

Answered by juhimittal
0

Answer:

9 upon 80 days. according to me

Similar questions