A and B can do a piece of work in 24 and 30 daysrespectively. Both started the work and worked for 6 days.Then B leaves the work and C joins and the remaining workis completed by A and C together in 11 days. Find the days in which C alone can do the work

A) 80 B) 100 C) 120 D) 130

Answers

Answered by kapilkumar48
1

Answer:

your answer is 80 days

C can finish work in 80 days

Answered by ytssdas1156
1

Answer:

I think answer is 120 days