A and B can do a piece of work in 24 days. After they have worked together for 15 days, B leaves and A completes the remaining work in 15 days. In how many days B alone do the work?
Answers
Answer :-
A and B can do a piece of work in 24 days.
Let us assume that the total amount of work = 24 units
So , A and B together can complete
Then ,
After they have worked together for 15 days, B leaves...
So , work done in 15 days
Remaining work
A completes the remaining work in 15 days
A completes the 9 units work in 15 days
so , in one day A completes
A = 0.6
Put this in equation 1
We have to find in how many days B alone do the work?
So , total amount of work = 24 units
B complete 0.4 unit per day
Then ,
B alone can complete the work in 60 days
Answer:
Step-by-step explanation:A and B can do a piece of work in 24 days.
Let us assume that the total amount of work = 24 units
So , A and B together can complete
Then ,
After they have worked together for 15 days, B leaves...
So , work done in 15 days
Remaining work
A completes the remaining work in 15 days
A completes the 9 units work in 15 days
so , in one day A completes
A = 0.6
Put this in equation 1
We have to find in how many days B alone do the work?
So , total amount of work = 24 units
B complete 0.4 unit per day
Then ,
B alone can complete the work in 60 days