Math, asked by ananyajahagirdar9, 5 hours ago

A and B can do a piece of work in 24 days. After they have worked together for 15 days, B leaves and A completes the remaining work in 15 days. In how many days B alone do the work?

Answers

Answered by hiteshgyanchandani6
4

Answer :-

A and B can do a piece of work in 24 days.

Let us assume that the total amount of work = 24 units

So , A and B together can complete

 =  \frac{24}{24}  = 1 \: unit \: per \: day

Then ,

A  +  B = 1 \\ B = 1 - A \:   -  -  -  - 1

After they have worked together for 15 days, B leaves...

So , work done in 15 days

 = 15 \times 1 = 15 \: units

Remaining work

 = 24 - 15 = 9 \: units \:

A completes the remaining work in 15 days

A completes the 9 units work in 15 days

so , in one day A completes

 =  \frac{9}{15}  = 0.6 \: unit \: per \: day

A = 0.6

Put this in equation 1

B = 1 - A  \\ B = 1 - 0.6  \\ B = 0.4 \: unit \: per \: day

We have to find in how many days B alone do the work?

So , total amount of work = 24 units

B complete 0.4 unit per day

Then ,

 =  \frac{24}{0.4}  = 60 \: days

B alone can complete the work in 60 days

Answered by frostygamer2010
0

Answer:

Step-by-step explanation:A and B can do a piece of work in 24 days.

Let us assume that the total amount of work = 24 units

So , A and B together can complete

Then ,

After they have worked together for 15 days, B leaves...

So , work done in 15 days

Remaining work

A completes the remaining work in 15 days

A completes the 9 units work in 15 days

so , in one day A completes

A = 0.6

Put this in equation 1

We have to find in how many days B alone do the work?

So , total amount of work = 24 units

B complete 0.4 unit per day

Then ,

B alone can complete the work in 60 days

Similar questions