Math, asked by sahaeti1997, 2 months ago

A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after sometime and B completed remaining work in 17 days. After how many days did A leave? ​

Answers

Answered by meherg21
0

see attached photos to your answer

B Completes remaining work in 17days. It means he had done

17×4=68 unit of work.

140−68=72units

72 units of work would have been done by A and B together so they had completed in

72/5+4= 8 days

A leaves after 8 days